The Yoogali Levee Stage 2A and 2B is part of Griffith City Council’s flood mitigation measures.
Construction work of Stage 2A and 2B will involve raising the road from Bosanquet Road to Newman Road (Stage 2A) and an earthen levee on the channel bank from Burley Griffin Way to Bosanquet Road (Stage 2B). Two culverts in this area were previously upgraded to increase their capacity in preparation for these works.
The Yoogali Levee Stage 2A and 2B is part of Griffith City Council’s flood mitigation measures.
Construction work of Stage 2A and 2B will involve raising the road from Bosanquet Road to Newman Road (Stage 2A) and an earthen levee on the channel bank from Burley Griffin Way to Bosanquet Road (Stage 2B). Two culverts in this area were previously upgraded to increase their capacity in preparation for these works.
Page last updated: 26 Mar 2025, 11:32 AM
Project update snapshot
5 March 2025
Yoogali Levee has finished this stage
Yoogali Levee from Bosanquet Road to Newman Road (Stage 2A) and Burley Griffin Way to Bosanquet Road (Stage 2B) work commences.
26 March 2025
Yoogali Levee has finished this stage
Road Closure – McCormack Road
14 May 2025
Yoogali Levee is currently at this stage
Road raising works for Stage 2A (Newman Road to Bosanquet Road intersection) are progressing well. With the subbase completed, kerb and gutter is now being installed on the northern side of McCormack Road from Newman Road to the Bosanquet Road intersection this week.
Kerb and gutter along the channel bank in Stage 2B (Bosanquet Road intersection to Burley Griffin Way) will also be installed soon, then earthworks on the channel bank will commence.
30 June 2025
this is an upcoming stage for Yoogali Levee
This project is expected to be complete by 30 June 2025, weather permitting.