Exciting developments are underway at Lake Wyangan, enhancing its appeal and sustainability for the Griffith community.
South Lake Wyangan Water Treatment
Aiming for a healthier lake ecosystem, South Lake Wyangan is receiving an environmentally sustainable treatment using Enviro – Diatomix. This innovative approach targets Blue Green Algae (BGA) reduction while promoting ecological balance.
Duration: Initial dosing will be carried out weekly dosing for 18 weeks (concluding December 2024), followed by regular ongoing treatments.
Results: Results of the treatment’s effectiveness should be known within 6–12 months, during which further analysis will provide conclusive evidence. If successful, Council plans to expand the initiative to include North Lake Wyangan.
Foreshore Development: Inclusive Play for All
Thanks to $1,030,000 from the Local Roads and Community Infrastructure Program (LRCIP) Phase 4, Council is delivering a new, inclusive foreshore playground. Expected to open by April 2025, this facility caters to children of all abilities with features like:
Adventure Multiplay Playground: Climbing nets, slides, and ground-level activities.
Fun Elements: Sand Factory, Flying Foxes, and more. Shaded areas, requested during community consultations, ensure comfort for all visitors.
Lake Wyangan’s dual focus on environmental sustainability and family-friendly amenities is set to make it a thriving destination for residents and visitors alike!
Exciting developments are underway at Lake Wyangan, enhancing its appeal and sustainability for the Griffith community.
South Lake Wyangan Water Treatment
Aiming for a healthier lake ecosystem, South Lake Wyangan is receiving an environmentally sustainable treatment using Enviro – Diatomix. This innovative approach targets Blue Green Algae (BGA) reduction while promoting ecological balance.
Duration: Initial dosing will be carried out weekly dosing for 18 weeks (concluding December 2024), followed by regular ongoing treatments.
Results: Results of the treatment’s effectiveness should be known within 6–12 months, during which further analysis will provide conclusive evidence. If successful, Council plans to expand the initiative to include North Lake Wyangan.
Foreshore Development: Inclusive Play for All
Thanks to $1,030,000 from the Local Roads and Community Infrastructure Program (LRCIP) Phase 4, Council is delivering a new, inclusive foreshore playground. Expected to open by April 2025, this facility caters to children of all abilities with features like:
Adventure Multiplay Playground: Climbing nets, slides, and ground-level activities.
Fun Elements: Sand Factory, Flying Foxes, and more. Shaded areas, requested during community consultations, ensure comfort for all visitors.
Lake Wyangan’s dual focus on environmental sustainability and family-friendly amenities is set to make it a thriving destination for residents and visitors alike!
Lake Wyangan Catchment Management Committee recommends:
Recruitment for the Lake Wyangan Project Officer position be suspended for up to 12 months.
A further report on the position to be prepared by January 2026.
14 March 2023
Griffith City Council adopts the Committee's recommendation.
May 2023
Lake Wyangan has finished this stage
Pumping infrastructure installed at South Lake to direct water to Murrumbidgee Irrigation drainage channels.
Pumping commenced, achieving:
Lowering water levels in both lakes to protect adjacent properties and infrastructure.
Improving water circulation and salinity levels.
September 2023
Lake Wyangan has finished this stage
Adoption of the Master Plan for Western Foreshore Improvements.
$2.03M allocated for Stage 1 implementation, expected completion by June 2024.
24 October 2023
Lake Wyangan has finished this stage
Council decides to apply for a Special Rate Variation (SRV) of 10.5% annually for three years (2024/25–2026/27).
Commitment made to achieve $1M in annual cost savings from 2024/25, including removing the Lake Wyangan Project Officer role.
27 October 2023
Lake Wyangan has finished this stage
2,500 ML of water pumped from South Lake. Pumping continues.
First Quarter 2024
Lake Wyangan has finished this stage
Completion of the initial pumping phase for South Lake. Pump infrastructure relocated to a permanent site.
21 November 2024
Lake Wyangan has finished this stage
Lake Wyangan’s foreshore redevelopment given the green light.
18-week treatment trial Enviro – Diatomix to improve water quality expected to be completed by early 2025. The sustainable treatment carried out in the South Lake. If successful, it is hoped Council will see a reduction in Blue Green Algae (BGA) and the overall health of the Lake’s ecosystem enhanced.
2025
Lake Wyangan is currently at this stage
Early 2025:
Foreshore enhancement works underway.
Throughout 2025:
Continued water testing and timely public updates on safety conditions.